Gloucester Community Solar Farm

Energise Gloucester is working with Komo Energy to develop the Gloucester Community Solar Farm. Energise Gloucester and Komo Energy are committed to giving local businesses, contractors and suppliers an opportunity to deliver or participate in the delivery of the Gloucester Community Solar Farm.

The Gloucester Community Solar Farm will be a 500 kW AC solar farm located near Gloucester and will make 25% of the electricity generated available to economically disadvantaged households at a discounted cost.

Komo Energy will shortly issue a Request for Proposals to suitable qualified contractors for the design and construction of the Gloucester Community Solar Farm. This expression of interest will help identify suitable local contractors that might wish to participate in the Request for Proposals process. It will also identify contractors and suppliers that may wish to be considered for subcontracting opportunities.

This project is supported by funding from the NSW Government.

Energise Gloucester Inc. acknowledges the funding support from the NSW Government under the Regional Community Energy Fund.

The Opportunities

We are seeking expressions of interest for the following activities:

1. Full-Scope Design And Construction

Interested parties are invited to express their interest for the full-scope design and construction of the Gloucester Community Solar Farm. Suitably qualified parties will be issued with the Request for Proposals in due course.

2. Subcontracting Opportunities

Interested parties are invited to express their interest for subcontracting opportunities. Details will be passed on to prospective head contractors as part of the Request for Proposal package.

(a) engineering
(b) geotech
(c) civil works (drive-way upgrade, trenching, site preparation)
(d) fencing works
(e) transport & logistics
(f) piling
(g) mechanical works (erection of mounting structure and mechanical (not electrical)
installation of PV modules)
(h) electrical works (solar DC installation to inverters)
(i) HV electrical works (network connection)
(j) site security
(k) plant & equipment hire
(l) rubbish & waste removal
(m) construction amenities / temporary building
(n) construction utilities (electricity, potable and non-potable water)
(o) signage
(p) photography (including time lapse) / drone footage
(q) visualisations

Next Steps

Design and Construction

If you would like to be considered for inclusion in the Request for Proposal for the full-scope design and construction of the Gloucester Community Solar Farm, please provide your details by either clicking on the button below or through this link: Gloucester Design and Construct.
Following review of your details, we may issue a Confidentiality and Process Agreement.


Subcontractor EOI

If you would like your details to be passed on in the Request for Proposal as a potential subcontractor, please provide your details by either clicking on the button below or through this link: Gloucester Subcontracting Opportunities.

Closing Date for this Expression of Interest
Friday 26 February 2021 at 12:00 pm AEST

Contact Details:

Gerald Arends
Director
Komo Service Pty Ltd
0468 851 854
gerald@komoenergy.com.au

Peter Buettel
Construction Manager
Energise Gloucester Inc
0429 208 944
buettel@ozemail.com.au